weeks 28 and 29: more progress on external wall insulation

Fron of house EWI

The external insulation progressed well (until we ran out) and the house is beginning to be transformed. I’m sure we’re the talk of the neighbourhood – ‘what on earth are they doing?’ Weather permitting, the rendering will start next week. and it will begin to look a bit more normal.

North Front EWI

Another week, or so and the insulation should be complete on the external – a fair bit to do on internal insulation works – particularly suspended floor and loft.

weeks 28-29: staircase goes in

Stairs from bottom Stairs from top

The new staircase was installed over the last couple of weeks. We were keen to have a curve on the turn on the stairs at the top and the joiner has made a lovely job of it. As the photo top left shows, the carpenters have started to build a curved wall from the hall to wrap around the stairs. Access to our new extension at last – feels like we are getting nearer to the end of the build now!